Background

This 14 ton filling machine was too large to be
moved into the filling area, as the doorways and
accessways were too small.

Our client arranged for removal of a section of the
roof and we then utilised a large mobile crane to
hoist the filler into the factory, where we could
continue with the assembly of the machine.